Egbema Valve Change-Out

Replacement of 5 Nos failed valves @Egbema Manifold. The project intention was to restore the facility to its optimum condition and to enable proper control of the valves. All 5 Cameron ball valves were installed following these steps:

  • Draining the Line
  • Unbolting of Valves (16” x 600#,14”x600#,12”x600#,12×600#,6×600#)
  • Removal of valves (5 Nos)
  • Installation of New valves
  • Bolting of the New Valves
  • Torquing of Valves
  • Cleaning & Painting of Valves